Phase 1 will involve the installation of a single point of generation at an 11kV substation site. The key objective of this phase will be to initiate, develop and deploy the engineering interface, commercial arrangement and first stage generation control methodology.
Phase 2 will utilise existing network connected generation along with strategically placed generation connected to an adjacent section of 11kV network, which will be a test within a more complex network environment. This will provide a platform for commercial arrangements and control methodologies to be further developed.