Oct 2013
Electricity Distribution
Impact of Electrolysers on the Distribution Network
SSET1010
Live
Oct 2013
Mar 2015
Scottish and Southern Electricity Networks
SSEN Future Networks Team
Click here to send a question to the contact.
LCN Fund Tier 1
None
Electric Vehicles
£753,000.00
To design and test an operational system for the safe, efficient operation of an electrolyser connected to the distribution network and establish a commercial framework for carrying out trials. To allow us to assess impacts of a large scale electrolyser on the network and produce a technical design for the ANM system which will allow a full range of trials to be undertaken.
  1. Demonstrate and understand safe and efficient connection and operation of electrolysers and their impact on the system;

  2. Develop operational strategies to minimise the potential impact of electrolysers on the network

  3. Identifying the potential to provide other network services