Mar 2013
Electricity Transmission
Fault Current Distribution in New Type of EHV cables
Reference:
Status:
Live
Start Date:
Mar 2013
End Date:
Unknown
Funding Licencee(s):
National Grid Electricity System Operator
Contact:
National Grid TO Innovation Team
Click here to send a question to the contact.
Funding Mechanism
Innovation Funding Incentive
Research Area:
None
Core Technology(ies):
Asset Management
Estimated Expenditure:
£81,000.00
Introduction:
Although Oil filled cables have well-established IGR and cable factors are set out in ER S34 (A guide for Assessing the Rise of Earth Potential at Substation Sites), XLPE cables have had no such study conducted on them. It is vital to understand the electrical properties of the cable sheath in returning some of the earth fault current as this is a key factor in the Ground Current Return (IGR). In order to analyse new types of XLPE cables, it is necessary to calculate cable parameters to a high degree of accuracy by software packages, numerical methods and formulae. This allows the effect of important variables upon IGR to be calculated. At present time specialist contractors are utilised to calculate the IGR for any cable run. This project aims to codify this knowledge and integrate this into Digslient so IGR for faults can be calculated as a standard procedure.
Objectives:
To derive and calculated the IGR for faults on XLPE cable. These derivations can then be utilised to calculate cable factor for different XLPE cable. These cable factors are then to be integrated into Digslient to enable fault current calculations to be carried out semi autonomously.
Related Links
National Grid Innovation Page on Jul 15, 2013
http://www.nationalgrid.com/corporate/About+us/innovation
National Grid Innovation Funding Incentive and Annual Report(s) on Mar 13, 2013
http://www.nationalgrid.com/uk/Electricity/Info/IFI/