Apr 2013
Electricity Transmission
Portable Earthing
Live
Apr 2013
Unknown
National Grid Electricity System Operator
National Grid TO Innovation Team
Click here to send a question to the contact.
Innovation Funding Incentive
None
Health and Safety
£97,000.00
An earthing project with an emphasis on health and safety.
The purpose of this project is two fold firstly work is being undertaken to gain an understanding of how substation Portable Primary Earths perform over extended application periods and to declare a maximum continuous current rating of substation PPE’s under induced current conditions. Secondly work is ongoing to develop a machine to enable the installation / removal of substation portable earths to be completed in a controlled and safe manner.