Mar 2018
Gas Distribution
Smart SLG Phase 1 – Automated plans
NIA_NGN_223
Complete
Mar 2018
Nov 2018
Northern Gas Networks
Ben Loker
Click here to send a question to the contact.
Network Innovation Allowance
None
Control Systems, Health and Safety, Stakeholder Engagement and Gas Distribution Networks
£160,000.00
Phase1 will focus on:
• Selecting an agreed set of Chapter 8 Traffic Safety Measures and Signs for Road Works and Temporary Situations scenarios. In partnership with NGN
• Writing the rules for these scenarios to automatically generate the plans
• Selecting and agreeing a study area
• Creating the required symbology for the plans.
• Providing the ability to:
o Select an area of the road network.
o Based on the selection run an automated process 
o Produce a plan output complying to chapter 8 with correct symbology as a PDF
• Provide NGN with a desktop or mobile environment they can test the scenarios in their own offices.  This will be limited to three people
• Demonstrate the (proof of concept) POC to interested local authorities 
Phase1 will focus on:
Selecting an agreed set of Chapter 8 Traffic Safety Measures and Signs for Road Works and Temporary Situations scenarios. In partnership with NGN
Writing the rules for these scenarios to automatically generate the plans
Selecting and agreeing a study area
Creating the required symbology for the plans.
Providing the ability to:
o Select an area of the road network.
o Based on the selection run an automated process 
o Produce a plan output complying to chapter 8 with correct symbology as a PDF
Provide NGN with a desktop or mobile environment they can test the scenarios in their own offices.  This will be limited to three people
Demonstrate the (proof of concept) POC to interested local authorities