May 2017
Gas Distribution
H21 - Keighley and Spadeadam designs
NIA_NGN_210
Complete
May 2017
Apr 2018
Northern Gas Networks and National Grid Gas Distribution
NGN - Dan Sadler Cadent - Lorna Millington
Click here to send a question to the contact.
Network Innovation Allowance
None
Gas Distribution Networks
£357,333.00
  1. Undertake the design (and subsequently tender the build) which will be required to enable modifications to the Keighley site which will facilitate the experimental testing plan for phase 1a) background testing of the 2017 H21 NIC bid (See ISP)
  2. Undertake the design (and subsequently tender the build) which will be required to enable modifications to the Spadeadam site which will facilitate the experimental testing plan for phase 1b) background testing of the 2017 H21 NIC bid (See ISP)
  3. To obtain design approval form DNVGL (akin to a G17 procedure) for the designs
  4. To obtain design approval form the HSL that the final design should meet the objectives of the experimental testing plan.

The project scope has been developed to deliver the following objectives;

 

  1. Scope of Work – As a project team agree the scope of the work, including equipment to be tested, measurements parameters and tests to be conducted
  2. Design – the objective for the design phase would be to complete a compliant design that is approved by the Design Assurance Authority. 
  3. Design Assurance – the Design Assurance process is conducted with agreement by all parties
  4. Project - The facility should be designed to facilitate the various tests that are to be conducted with the minimum amount of reconfiguration
  5. Measurement – working with NPL decide the process measurements required and design the location for the instrumentation as well as suitable fittings for them and the correct environmental condition (habitat for the testing facilities)
In considering the success of the project the following success criteria as a minimum output from the project to provide Technical and Strategic Evidence:

  1. Final design and design assurance for Keighley site

  2. Approval from the HSL that the design at Keighley meets with the objectives of the experimental testing plan

  3. Final design and design assurance for spadeadam site

  4. Approval from the HSL that the design at spadeadam meets with the objectives of the experimental testing plan