Close
Forgotten Password?
Login?
Register Me
Home
About
Contact
More
More
Network Operators
Funding Timeline
LCNI Presentations
Annual Innovation Summary
Funding Documents
Document Templates
Events
Login
Home
About
Contact
Network Operators
Funding Timeline
LCNI Presentations
Annual Innovation Summary
Funding Documents
Document Templates
Events
Project Details
R
eport
pt
P
rint
rn
D
ownload
/L
Save
Share
Share
Facebook
Twitter
Google
Gas Transmission
Project Details
Documents
Ideas for future projects?
Apr 2018
Gas Transmission and Gas Distribution
European Pipeline Research Group 2018
Reference:
NIA_NGGT0130
Status:
Complete
Start Date:
Apr 2018
End Date:
Apr 2019
Funding Licencee(s):
National Grid Gas Transmission and Cadent
Contact:
Rob Bood (NGGT) & Luke Hollis (Cadent Gas)
Click here to send a question to the contact.
Funding Mechanism
Network Innovation Allowance
Research Area:
GD - Reliability and maintenance and GT - Reliability and maintenance
Core Technology(ies):
Estimated Expenditure:
£99,000.00
Introduction:
Objectives:
National Grid and Cadent Gas want to continue to establish best practice technologies and techniques in order to allow the safe, reliable, efficient and economic use of the gas network, while reducing impact on the environment. By participating in EPRG, National Grid and Cadent Gas have benefitted, and will continue to benefit from the international experience of the other member companies’ representatives, while benefiting from significant leverage on project activity from the other member companies.