Jul 2018
Gas Transmission
Valve Pits Insulation
NIA_NGGT0127
Complete
Jul 2018
Dec 2018
National Grid Gas Transmission
David Kerr
Click here to send a question to the contact.
Network Innovation Allowance
GT - Reliability and maintenance and GT - Environment and low carbon
£221,250.00
Replace the existing fiberglass with 4 cm thick plastic coated insulation sheets in the gussets of the steelwork about the pits and assess the effectives of the new material.