Mar 2016
Gas Distribution
Concrete Removal System for Multi-Occupancy Buildings (MOBs)
NIA_NGGD0076
Complete
Mar 2016
Mar 2017
National Grid Gas Distribution
Joe McShane (Innovation Project Manager)
Click here to send a question to the contact.
Network Innovation Allowance
None
Gas Distribution Networks
£43,911.00
The Scope of this proposal is to design, manufacture and trial (laboratory and field) the new product to initially prove an improved method of securing riser pipework to walls whilst also improving repair activities on gas risers in MOBs.

The output would consist of a product for concrete removal tested in both a laboratory and field environment.

The Project seeks to prove that the a currently conceptual approach to the problem is able, through trialling, to demonstrate that it offers a viable, cost effective and less customer disruptive alternative to inspecting and repairing/replacing gas risers.

The Project can be considered a success if, upon completion of work:

  • The product has demonstrated capability of performing the desired tasks

  • Feedback from the GDN engineers involved in the final stages of the project do not prohibit the further roll-out of the solution into normal working practice.