Jul 2015
Gas Distribution
Leyland CNG Filling Station
NIA_NGGD0063
Complete
Jul 2015
May 2017
National Grid Gas Distribution
Philip Halsey – National Grid, John Baldwin - CNG Services Ltd
Click here to send a question to the contact.
Network Innovation Allowance
None
Gas Distribution Networks
£693,705.00
The scope of the project is to design, install and commission the LTS connection to the CNG filling Station and generate a report on the efficiencies of a station connected to a higher pressure tier system.

  1. Design and install a Steel pipeline and appropriate civils protection to connect the filling station to the LTS

  2. Record the findings of the project by:
  • Outline benefits with back up data

  • Record the actual data from the project

  • Analysis of the data

  • Provide a detailed report and record the findings

The objective of the project is to demonstrate the increased efficiencies and benefits of the use of LTS connected CNG filling stations.

The report will show evidence of the effectiveness and efficiency of an LTS connected CNG filling station and the GHG and emissions benefits from dedicated CNG trucks operated by a supplier.

Financial benefits will also be included as part of the detailed analysis in the report.