Apr 2013
Electricity Distribution
IntelliTeam DA
2007_07
Live
Apr 2013
Unknown
Scottish and Southern Electricity Networks
SSEN Future Networks Team
Click here to send a question to the contact.
Innovation Funding Incentive
None
High Voltage Technology
£209,400.00
A pilot scheme to evaluate the performance of next generation network automation to automatically reconfigure the network into isolatable sections.
It is proposed to establish a pilot scheme to evaluate both the overhead and underground plant functionality and how they can interact on mixed networks. The pilot will be split into three phases. Phase 1 is to understand the costing and technical requirements for interfacing onto our network and the design of an underground circuit breaker. Phase 2 is to install the equipment on a section of overhead network with Phase 3 on a section of underground network.