26 Jan 2018
Ofgem announces decision to approve National Grid's OSEAIT NIC Project's substation conversion costs
As stipulated by the Project Direction, NGET was required to submit a final estimate of the substation conversion costs to Ofgem before any of the associated construction works could begin.
This letter outlines the reasons for our decision to accept NGET’s final estimate and return funding that is not required by NGET to customers.

Network Innovation Competition – OSEAIT – Decision to approve substation conversion costs